Construction at Watermark on Mainstreet (Vanterra) is moving along at an impressive rate.
Projects taking place or completed include:
Building 1 slab is complete.
Underground plumbing is underway in buildings 2, 6 and 9.
Building 8 footings are complete.
All of the garage footings are finished.
The sanitary and storm sewers are close to 90% complete.
We are excited by the progress at Watermark at Mainstreet over the last few months. We look forward to sharing future updates with you as more slabs are poured and the first buildings go vertical.